Chấm dứt hợp ồng: nhiệt điện sông hậu 2 và thông báo bộ công thương
Chấm dứt hợp ồng: nhiệt điện sông hậu 2 và thông báo bộ công thương
Treatment of the Project Heat Energy Sông HậU 2: TV2 loses the order package worth $ 1.1 billion $
The Ministry of Industry and Commerce recently published the letter 4579/BCT-DL of July 1, 2024, in which the company with limited liability electricity SôNG Hậu 2 is informed that the bot contract of the project Heat Energy Sông Hậu 2 is terminated due to inadequate financial regulations of the company.
The Ministry of Industry and Trade on November 9, 2023 sent a letter to the Toyo Ink Group Berhad on November 9, 2023 and the company with limited liability electricity Sông Hậu 2 at which the time and the conditions for the resolutions of the project were determined.On April 1, 2024, the Ministry of Industry and Trade again announced the company with limited liability electricity SOông Hậu 2 that there is "violations of the project developer" and the intention of terminating the bot contract.
At the beginning of June 2024, the Toyo Ink Berhad signed a loan contract of $ 980 million with the EXIMBANK Malaysia for the Heat Energy Sông Hậu 2 project to support design, device procurement, construction and commissioning of the project.
until June 30th, the company with limited liability electricity Sông Hậu 2 could not ensure sufficient funding for the project. According to the regulations, the Ministry of Industry and Commerce has therefore officially communicated the effectiveness of the end of the project of the project of the project for the company with limited liability for electricity Sông Hậu 2.
The importance of the project for TV2
The thermal energy project Sông Hậu 2 is an important project in the eighth electricity plan, which has an output of 2,120mw and is invested by the Toyo Ink Group Berhad (Malaysia).
In March 2013, the PEC2 TV2 Corporation and Sunway Construction (Malaysia) signed a contract worth around $ 2.42 billion for project development. The contract of TV2 as part of this order package is an estimated 45% ($ 1.1 billion).
tv2 has a crucial role in the success of the thermal energy project Sông Hậu 2. At this year's annual shareholder meeting on June 14th, the CEO of TV2, Mr. Nguyễn Chơn Hùng, commented on the concerns of the shareholders regarding the risks of a contract termination. He emphasized: "June 30th is the defined deadline for ensuring financing. In fact, there are certain conditions that have to be met, including the most important, the initial investment sum.
Mr. Hùng added: "You should not only measure a company on a project. Sông Hậu 2 brings additional jobs for TV2. To grow, we have to concentrate more on innovations and create opportunities for the company.