New schedule for Saalebrücke in Weißenfels: Start of construction 2029

New schedule for Saalebrücke in Weißenfels: Start of construction 2029

Building project Delays In the new construction of the hall bridge in Weißenfels

The planned start of the new building of the large Saalebrücke in Weißenfels causes discussions in the city. The start of construction was originally scheduled for this year, but extensive planning extensions will now take until 2029.

Advanced planning lead to delays

The city administration has announced that the bridge should be wider to enable a separate bike path. This decision was made to increase the safety of both pedestrians and cyclists. The need for more space means that the planning must be significantly revised.

original building delay by species protection

A previous shift by one year was already in September last year when the house pigeons protected in the bridge pillars brooded. These birds are subject to species protection, which required additional examination and planning.

cost burden for the city

The current estimates amount to around 18 million euros for the new bridge. This high cost burden, coupled with constant delays, leads to frustration among the population and many city representatives.

reactions of the city administration

The Mayor of Weißenfels, Martin Papke, expressed very angry about the developments. His clear message: "I'm pissed off." He emphasizes that the long-term planning for cycling and footpaths are no longer conveyed to the citizens of how long they have to wait for an improvement in the infrastructure.

meaning for the community

The delay in the new bridge not only affects local traffic and footpath planning, but also reflects a bigger problem: the challenges in the implementation of sustainable mobility concepts in small cities. Residents hope for an early solution to improve security on the streets and at the same time meet the needs of all road users.